Home

 

goldspinningcross.gif (8977 bytes)

This Page Updated 


March 23rd, 2009


 

Go to our Upcoming Events page to see what we have planned for 2009.

Latest Changes

bullet This is where we'll announce the most recent changes to the ORC historic site. If you've visited us before and want to know what's changed, take a look here first.

 

2007-08 Brought Numerous Changes to The Old Rugged Cross Church

The decision was made NOT to move the old church temporarily and NOT to put a full basement under the church. The estimated cost of the phase ($237,000) kept us from making any progress on the restoration for several years, and we feel it's because it was OUR plan and NOT GOD'S plan to have a basement under the church. Consequently, as soon as the decision was made to abandon that plan, God opened numerous doors and the wheels of progress began to turn so fast it left us all breathless.

Here's what was accomplished in 2007:

bulletA replica of the original bell tower was constructed and lifted onto the church on September 5 with the original bell inside.
bulletDamaged siding was removed from the east wall and replaced with new wooden boards that are duplicates of the original double Dutch lap boards.
bulletNew boards were then used to replace half of the boards on the north wall of the building, saving half of the original boards on that wall.
bulletWooden shutters were removed from all main floor windows and plastic sheeting was removed from the upper level windows.
bulletNew window frames were constructed and Lexan windows were installed in all windows.
bulletA crawlspace was dug under the entire building; concrete flooring was poured, concrete footers were poured around the perimeter of the building and a permanent concrete wall foundation was poured around all but the west (front) wall.
bulletThe outer walls of the foundation were tarred and dirt was backfilled against them for the winter.
bulletA very generous and beloved supporter, Tom McCollum from Augusta, Georgia, made and donated a walnut Communion Table for the sanctuary.

Funds were all but totally depleted to accomplish the above, but what an accomplishment!

Here's what was accomplished in 2008:

bulletThe foundation for the west wall was completed.
bulletA new wooden sub-floor was installed in the sanctuary.
bulletThe original side door was repaired and will be installed in 2009.
bulletNew front doors and hardware were ordered.
bulletBricks were laid from Vermont Street to the front door of the church. (Many have already been purchased and are engraved with names and personal messages.)
bulletLandscape was excavated around the building.
bulletThe entire exterior of the building received two coats of white paint.
bulletOur very generous and beloved supporter, Tom McCollum from Augusta, Georgia, made and donated a table for the entry vestibule, two wall mounted boards for attendance and hymn numbers for the sanctuary, and five offering poles (a nearby resident, who was baptized in that church, says there were no offering plates, but bags on poles to take up the offering). A wonderful member of The Hillcrest Baptist Church in Augusta, Georgia made the red velvet bags for the poles. They are a perfect match to the red velvet on top of the original pulpit, which will be back in the old church again this summer.

Here's what is scheduled for 2009:

bulletThe new front doors have been installed and will be painted with dark green milk paint.
bulletThe repaired original side door will be installed.
bulletAll woodwork will be temporarily removed from the sanctuary and will be stripped and refinished.
bulletWork will begin to repair “fixable” plaster and re-plaster walls in the sanctuary.
bulletA ceiling will be constructed in the sanctuary.
bulletRefinished woodwork will be replaced
bulletWork will begin to repair soffit, facia and rafter tails (which will seal the building).
bulletBasic Electric service will be installed

Some of the above items will depend on funds raised this year. Supporters have been generous, which has enabled all the work done to date. The current economic catastrophe has slowed donations considerably, but work will continue as funds allow.

What’s left?

bulletThe roofOnce all of the above is completed, the roof must be addressed. The current metal roof was a temporary measure to keep out the weather, as the layers beneath it are an eclectic mixture of a few of the original cedar shingles, old corrugated sheet metal pieces, and the original sheathing boards, many of which are rotting. The new roof will be a replica of the original cedar shingles.
bulletChimney repairs
bulletInstalling walls and ceilings in the kitchen and upper room
bulletCompleting the electrical package
bulletInstalling heating and air-conditioning to preserve the antiques (once this is done, the original pump organ can be returned to the church, along with other artifacts awaiting their church home).
bulletPainting interior walls until money is available to replicate the original wallpaper patterns
bulletReplicating the original pews
bulletInstalling replica painted glass windows

 

Thank you for your interest and your support. For more information, please contact the ORC Foundation via phone at 269-683-4540, via e-mail at ORCF@aol.com, or via mail at:


The Old Rugged Cross Foundation Inc.
PO Box 41
Niles, MI 49120

The Old Rugged Cross Foundation, Inc.
PO Box 41, Niles, MI 49120
Phone: 269-683-4540 Fax: 269-683-4315
E-Mail: ORCF@aol.com
Websites:

http://www.theoldruggedcrossfoundation.org

 http://www.the-oldruggedcross.org

 

Press Releases

These are the press releases we've issued over the last year. You may want to search for topics by keyword.

bulletNone at this time.

 

 

Recent Media Coverage of:

THE OLD RUGGED CROSS FOUNDATION, Inc.

 

bullet'Old Rugged Cross' site in Cass County now on Historic Register; The Herald Palladium. Monday, July 01, 2002